Genco Construction

Our Process

Timeline expectations

Realistic durations for kitchen, bathroom, and addition projects in Dallas-Fort Worth — plus what controls schedule and how we keep your project on track.

Typical ranges

How long it actually takes

Pre-construction (design, selections, permitting) happens before demo. Construction is the active build phase. Most homeowners underestimate pre-construction; we plan for it.

Project typePre-constructionConstruction
Guest / hall bathroom remodel1–2 weeks2–4 weeks
Primary bathroom remodel2–4 weeks4–6 weeks
Kitchen remodel (standard)3–6 weeks5–8 weeks
Kitchen remodel (complex / structural)4–8 weeks8–12 weeks
Attic conversion4–8 weeks9–15 weeks
Second-story addition6–12 weeks12–21 weeks
Ground-level addition5–10 weeks11–18 weeks

Phase breakdown

Where the time goes

Construction time isn't evenly distributed — and the longest phase is rarely the visible one.

  • 20–30%

    Pre-construction

    Design, engineering (if needed), selections, procurement, permitting. This phase prevents 80% of construction delays.

  • 15–20%

    Demo + rough-in

    Demolition, structural work, plumbing / electrical rough-in, HVAC modifications. Inspections gate the next phase.

  • 35–45%

    Build-out

    Waterproofing, tile, drywall, paint, trim, cabinet / vanity install, countertop templating. The longest phase.

  • 10–15%

    Finish + closeout

    Fixtures, glass, hardware, final electrical, punch list, cleaning, walkthrough. Quality lives in the details.

What causes delays

Six things that stretch a remodel schedule

Most schedule slippage is preventable — but only if you know what to plan for.

  • Permit / inspection cadence

    City review times vary: Dallas proper averages 3–4 weeks; suburban cities 2–6 weeks. Re-submittals add 1–3 weeks.

  • Custom or long-lead materials

    Custom cabinets (6–12 weeks), specialty tile (4–8 weeks), stone slabs (2–4 weeks), appliances (2–12 weeks), custom glass (3–6 weeks).

  • Structural changes & hidden conditions

    Old wiring, galvanized plumbing, rotted framing, foundation issues — only visible after demo. Budget 1–3 weeks for resolution.

  • Scope changes after work begins

    Mid-project changes require re-pricing, material sourcing, and schedule adjustment. Each change order typically adds 3–10 days.

  • Weather impacts

    Additions and exterior work are weather-dependent. DFW spring storms and summer heat can impact framing, roofing, and concrete work.

  • Selection delays

    Late tile, fixture, or cabinet decisions are the #1 controllable cause of delay. We guide selections before construction to prevent this.

How we protect the schedule

Four habits that keep projects on time

  • Selections guidance early

    We guide tile, fixtures, cabinets, and finishes before construction starts — so you're not choosing under pressure mid-project.

  • Procurement planning

    Long-lead items are identified and ordered during pre-construction. Cabinets, specialty tile, and appliances are staged before demo.

  • Trade sequencing

    Built around inspections, drying / curing times, and material deliveries for efficient flow with zero trade stacking.

  • Consistent communication

    Weekly updates and proactive decision requests keep decisions ahead of the build schedule — not behind it.

Frequently asked

Timeline & schedule questions

Bathrooms: 3–8 weeks construction. Kitchens: 6–16 weeks. Additions: 12–28 weeks. Pre-construction (design, selections, permitting) adds 1–12 weeks depending on complexity.

See detailed timeline ranges

The number-one controllable cause is late selections (tile, fixtures, cabinets). Other factors: permit review times, long-lead materials, hidden conditions, scope changes, and weather (for additions). Our pre-construction process addresses most of these.

Often, yes — especially for bathrooms and some kitchens. For major kitchen remodels, we recommend a temporary kitchen setup. For additions, most clients stay home since work is largely exterior until the tie-in phase. We discuss access, safety, and dust control before construction starts.

Dallas proper averages 3–4 weeks for plan review. Suburban cities vary: Plano and Frisco are typically 2–3 weeks; Southlake and Colleyville can take 4–6 weeks due to architectural review boards.

Ready when you are

Plan your project around a realistic timeline

Schedule a consultation and we'll map your full schedule — pre-construction through closeout — before any commitments are made.